Monday, September 20, 2021

Paving project - September 23-24

Finally, I was able to get the exact dates of our paving project.
Our contractors should be here on the 23rd (Thursday) from 7am to 10am for excavating and prep work. Actual paving will be done the next day, the 24th (Friday).
After that, in order to allow asphalt to cure, access to the driveway will be closed for 10 days.
 
Access should be fully restored on October 5th.

Please remember that we have an emergency exit door located in the back of the garage. You can also use this door to get into the garage from outside (the lock will open with the same key you use for other doors).

Thank you
Alex