Monday, September 9, 2024

Paving is tentatively scheduled for Thursday, September 12th

It looks like the driveway paving is tentatively scheduled for Thursday this week.
If all goes as planned the asphalt would need 72 hours to cure (to harden) before we can start driving on it. During curing the driveway will not be accessible at all.
Please expect the driveway to be open on Sunday night (September 15th).

Also, there is a chance that the street/sidewalk part of our project will be done on Tuesday or Wednesday this week and before paving. It is for connecting our new drainage system to the city drain.

Please stay tuned for latest updates and do not forget to wipe your feet before entering the building from the garage because the floor gets dusty with fine soil flying in every time when the gates get open.

We are almost done.
Thank you for your patience